NIXA BEGINS CONSTRUCTION ON AND LAYS OUT TIMELINE FOR 2019 BALLOT ISSUE PROJECTS
Nixa has been in the planning stages for the last several months getting ready to begin some of the major
construction projects from the April 2019 ballot issues.
Eagle Stadium's construction will begin in early 2020 and should be completed by the fall football season.
The stadium's new design has been adjusted over the past several months to ensure all needs and
requirements will be met for the high school and the district.
The stadium remodel will include all new bleachers, after the cost difference between keeping the current
ones with an addition and adding all new bleachers was found to be minimal.
A new concession stand and plaza area will allow fans and the community to gather before the start of the
game and experience more activities rather than just standing in line for hours before the game starts. The
visitor's section will have its own concession and restroom area.
Century's classroom addition will happen in the 2020-21 school year and will be open for the 2021-22
school year. This will allow the district to bring the 4th grade classes back home for that year.
Work on finalizing the plans for the Performing Arts Center will begin in the spring of 2020 to allow for the
bidding process to begin soon after and work to begin in the fall/winter of 2020.
For regular pictures and updates, make sure and visit www.nixabondissue.net.
Century Elementary's classroom additions
will begin in the spring/summer of 2020
and be completed by the fall of 2021.
/www.nixabondissue.net